The Move Seattle levy project was once supposed to be a RapidRide line opening in 2023. Here's what was built, what changed after business groups objected, and how it connects to Tuesday's transit vote.

Seattle and King County officials cut the ribbon this week on upgrades to King County Metro's Route 40, one of the city's busiest bus lines, The Urbanist reported Oct. 30. The route runs from downtown through Westlake, Fremont, Ballard and Crown Hill to Northgate.

If you ride the 40, or drive, bike or walk along it, the street has changed. According to The Urbanist, the finished work includes:

  • About three miles of business access and transit (BAT) lanes, mainly in Ballard, on both sides of the Fremont Bridge and on Westlake Avenue North.
  • 16 upgraded bus stops.
  • More than 6,000 feet of new sidewalk, plus new crosswalks and curb ramps.

About 9,000 people ride the route each day, which makes it one of Metro's most used. Early Metro data shows trips between Fremont and Ballard are about 11 percent faster, or about 90 seconds per trip on average, The Urbanist reported.

How long it took

The project was paid for by the 2015 Move Seattle levy, according to The Urbanist. It was first planned as a RapidRide line opening in 2023. In 2018 the city dropped the RapidRide plan, citing a budget shortfall and uncertain federal transit money. Later delays came from planning issues, budget turmoil and utility work, including about 200 feet of replaced water main.

Business groups pushed back along the way. The North Seattle Industrial Association objected to lost general traffic lanes and impacts on freight. The Fremont Chamber of Commerce and the Ballard Alliance raised concerns in a 2023 letter, pointing to lower ridership than before the pandemic. In response, The Urbanist reported, the city moved a Fremont bus stop, redesigned a crosswalk on Westlake Avenue North and committed to a freight-and-bus lane pilot there.

At the ribbon cutting, King County Executive Girmay Zahilay said the route "has become faster, safer, and easier to use." Mayor Katie Wilson said it shows the city can keep improving existing bus routes, according to The Urbanist.

What our records add

The Council's past fights. The Urbanist recalled that then-Council President Sara Nelson opposed the bus lanes in 2023 and in 2024 threatened to block transit projects through the budget. Nelson lost her 2025 reelection to Dionne Foster, who now holds Position 9.

Who represents the corridor. The 40 runs through three Council districts. Westlake is in District 7 (Robert Kettle). Fremont, Ballard and Crown Hill are in District 6 (Dan Strauss, the budget chair). Northgate is in District 5, held by appointee Debora Juarez until voters fill the seat.

The next transit money. Paving and sidewalks came from Move Seattle. The extra bus hours Seattle buys from Metro come from the city's transit sales tax, which is up for renewal Tuesday as Prop. 1. The mayor's 2027 budget assumes about $44.9 million from the measure for bus service (our story).

One Council budget proposal would use some of that money in the same corridor. Strauss's SDOT-001 would set aside $400,000 for a summer transit pilot to Golden Gardens Park from connecting bus stops such as a Ballard terminus at 15th Ave NW and NW Market St, according to Central Staff's SDOT proposal packet. Its co-sponsors are Kettle and Alexis Mercedes Rinck.

What's next

  • Tuesday, Nov. 3: voters decide Prop. 1 (our explainer).
  • Wednesday, Nov. 4: Strauss's balancing package shows whether the Golden Gardens pilot survives (meeting page).
  • Westlake Avenue North: the freight-and-bus lane pilot the city promised is still to come, The Urbanist reported.